Visit http://www.state.nj.us/transportation/ This project at the Fernwood Complex (NJ DOT maintenance yard) required extensive aerial cable distribution connecting approximately eighteen of the twenty-two buildings comprising the campus. The scope of this project included the installation of seven new telephone poles, 120 feet of underground raceway, aerial distribution of 825 pair copper and 216 strands of MM fiber to 18 buildings. Additionally, there were approximately 200 triplex voice and data station cables installed among the buildings receiving distribution cable. This project was completed ahead of the 16-week construction schedule under the management of Mr. Bainger. We are now performing qualified work under NJ State contract for other government sites as the opportunity arises.
 